Installation diagram and instructions for double speed chain conveyor line

The following is the core module decomposition and key step explanation of a typical double speed chain conveyor line installation diagram (based on conventional industrial scenarios):

Später diskutieren Teilen

Anhang

Installation diagram and instructions for double speed chain conveyor line

 

The following is the core module decomposition and key step explanation of a typical double speed chain conveyor line installation diagram (based on conventional industrial scenarios):

 

1、 Overview of Installation Diagram

 

 

(Note: The schematic diagram should include the following key component annotations)

 

Drive unit (motor+reducer)

Main/driven wheel set (including tension adjustment bolt)

Chain track (aluminum profile/steel support frame)

Double speed chain (with roller and fixture board slot)

Support tripod (height adjustable foot)

Blocker/positioning sensor (pneumatic or photoelectric)

Electrical control cabinet (PLC+frequency converter)

2、 Detailed installation steps

1. Basic framework installation

Support tripod positioning

Fix the anchor bolts according to the design drawings, with a spacing of ≤ 1.5 meters (increased to ≤ 1 meter in heavy-duty scenarios).

Use a laser level to calibrate the levelness of the frame, with an error of ≤ 1mm/meter.

Track splicing

The aluminum profile track is connected by internal hexagonal bolts, and a transition plate (gap ≤ 0.5mm) needs to be installed at the joint.

2. Chain and roller laying

Chain assembly

Spread the double speed chain in sections, ensuring that the direction of the rollers is consistent with the running direction (with the arrow pointing upwards).

Use specialized chain connectors to connect and maintain flexible chain link movement (no jamming during manual pulling test).

Tension adjustment

Reserve 5-10cm of tension stroke on the driving wheel side, and control the chain sag of ≤ 2% on the driven wheel side through adjusting bolts.

3. Driver system installation

Fixing of motor and reducer

The motor shaft and the driving wheel axis must be strictly coaxial (deviation ≤ 0.1mm) to avoid chain deviation.

Heavy duty line bodies need to be equipped with auxiliary support frames to prevent displacement caused by motor vibration.

Transmission chain/synchronous belt connection

Chain tightness: It is best to press the middle section with fingers and let it sag by 10-15mm.

4. Integration of functional modules

Barrier installation

The distance between the pneumatic blocker and the fixture plate should be maintained at 1-2mm, and the response time should be ≤ 0.1 seconds.

Sensor wiring

The signal line of the photoelectric sensor needs to be routed separately from the power line, with a spacing of ≥ 30cm, to avoid interference.

3、 Key precautions

Chain anti twist

During installation, it is prohibited to forcefully bend the chain, and the bending radius must be ≥ 30 times the chain pitch.

Lubrication requirements

Before the first operation of the steel chain, it is necessary to apply high-temperature lithium grease (thickness 0.1-0.3mm).

Security testing

Run without load for 24 hours, detect noise (≤ 75dB) and temperature rise (motor surface ≤ 60 ℃).

4、 Debugging and acceptance

Load testing

Apply pressure in stages at 50%/75%/100% of the nominal load and observe the deformation of the chain (≤ 3%).

Accuracy verification

Repetitive accuracy of fixture board positioning: ± 0.5mm (servo control scenario).

 

Note: Actual installation should refer to the CAD drawings provided by the supplier (including dimensional tolerances and force analysis). For complex lines, it is recommended to have professional engineers provide on-site guidance. If you need a complete schematic source file, you can contact the equipment supplier to obtain DWG/PDF format drawings.


Installation diagram and instructions for double speed chain conveyor line
The following is the core module decomposition and key step explanation of a typical double speed chain conveyor line installation diagram (based on conventional industrial scenarios):
Lange drücken, um den QR-Code zu identifizieren und Details anzuzeigen
Drücken Sie lange auf das Bild, um es zu speichern / zu teilen
Anfrage

在线询盘 Mehr+
  • 联系人 *

  • 手机 *

  • 描述

  • einreichen

  • Verifizierungs-Schlüssel
    Sie können nicht klar sehen? Ändern Sie einen
    Stornieren
    bestimmen

Beratungsprodukte:


Sie haben noch keine Produkte hinzugefügt!

Erfolgreich beitreten

概述

模块化托盘输送机具有平稳、干燥、洁净的特点,广泛应用于新能源电池输送线,包括电池装配线、锂电池PACK线和模组线

汽车零配件

汽车零部件组装线

Copyright: Shanghai Lingke Huakong Industrial Technology Co., Ltd

Onlineservice
Kontaktdetails
hotline
13391198429
working hours
Monday to Friday 8.30-17.30
Email address
lingkedgo@qq.com
QR-Code
QR-Code
Scan the code to follow, easily consult and inquire about prices
Onlineservice
Add WeChat friend to learn more about the product
Use Enterprise WeChat
"Scan" to join the group chat
Erfolgreich kopieren!
Add WeChat friend to learn more about the product
I see.