The following is the core module decomposition and key step explanation of a typical double speed chain conveyor line installation diagram (based on conventional industrial scenarios):
Später diskutieren
Installation diagram and instructions for double speed chain conveyor line
The following is the core module decomposition and key step explanation of a typical double speed chain conveyor line installation diagram (based on conventional industrial scenarios):
1、 Overview of Installation Diagram
(Note: The schematic diagram should include the following key component annotations)
Drive unit (motor+reducer)
Main/driven wheel set (including tension adjustment bolt)
Chain track (aluminum profile/steel support frame)
Double speed chain (with roller and fixture board slot)
Support tripod (height adjustable foot)
Blocker/positioning sensor (pneumatic or photoelectric)
Electrical control cabinet (PLC+frequency converter)
2、 Detailed installation steps
1. Basic framework installation
Support tripod positioning
Fix the anchor bolts according to the design drawings, with a spacing of ≤ 1.5 meters (increased to ≤ 1 meter in heavy-duty scenarios).
Use a laser level to calibrate the levelness of the frame, with an error of ≤ 1mm/meter.
Track splicing
The aluminum profile track is connected by internal hexagonal bolts, and a transition plate (gap ≤ 0.5mm) needs to be installed at the joint.
2. Chain and roller laying
Chain assembly
Spread the double speed chain in sections, ensuring that the direction of the rollers is consistent with the running direction (with the arrow pointing upwards).
Use specialized chain connectors to connect and maintain flexible chain link movement (no jamming during manual pulling test).
Tension adjustment
Reserve 5-10cm of tension stroke on the driving wheel side, and control the chain sag of ≤ 2% on the driven wheel side through adjusting bolts.
3. Driver system installation
Fixing of motor and reducer
The motor shaft and the driving wheel axis must be strictly coaxial (deviation ≤ 0.1mm) to avoid chain deviation.
Heavy duty line bodies need to be equipped with auxiliary support frames to prevent displacement caused by motor vibration.
Transmission chain/synchronous belt connection
Chain tightness: It is best to press the middle section with fingers and let it sag by 10-15mm.
4. Integration of functional modules
Barrier installation
The distance between the pneumatic blocker and the fixture plate should be maintained at 1-2mm, and the response time should be ≤ 0.1 seconds.
Sensor wiring
The signal line of the photoelectric sensor needs to be routed separately from the power line, with a spacing of ≥ 30cm, to avoid interference.
3、 Key precautions
Chain anti twist
During installation, it is prohibited to forcefully bend the chain, and the bending radius must be ≥ 30 times the chain pitch.
Lubrication requirements
Before the first operation of the steel chain, it is necessary to apply high-temperature lithium grease (thickness 0.1-0.3mm).
Security testing
Run without load for 24 hours, detect noise (≤ 75dB) and temperature rise (motor surface ≤ 60 ℃).
4、 Debugging and acceptance
Load testing
Apply pressure in stages at 50%/75%/100% of the nominal load and observe the deformation of the chain (≤ 3%).
Accuracy verification
Repetitive accuracy of fixture board positioning: ± 0.5mm (servo control scenario).
Note: Actual installation should refer to the CAD drawings provided by the supplier (including dimensional tolerances and force analysis). For complex lines, it is recommended to have professional engineers provide on-site guidance. If you need a complete schematic source file, you can contact the equipment supplier to obtain DWG/PDF format drawings.