The installation of the double speed chain pallet conveyor line needs to follow a systematic process, and the specific steps and technical points are as follows:
1、 Preparation before installation
Site planning and scheme design
Based on the terrain of the production workshop, material conveying distance, and load-bearing requirements, determine the conveyor line model and layout plan to ensure that the equipment size matches the site.
Inventory of tools and components
Prepare core components such as chains, sprockets, motors, brackets, etc., and check if tools such as wrenches and screwdrivers are complete. Confirm that the specifications of the components are consistent with the drawings.
2、 Installation of main structure
Bracket and base fixation
Starting/ending bracket: Reserve installation space at both ends of the conveyor line, and fix the bracket vertically to the ground with bolts to ensure a horizontal error of ≤ 2mm.
Base installation: Position the bolt holes according to the coordinate markings, calibrate with a spirit level, and tighten the base to ensure overall structural stability.
Assembly of conveyor frame
After cutting the steel and welding it into shape, it is necessary to maintain horizontal alignment during segmented connection. Before painting, the weld seam should be polished and rust proof treated.
3、 Power and transmission system configuration
Chain and sprocket installation
Lay the double speed chain flat on the conveyor track and adjust the tension to a sag of ≤ 2% of the chain length to avoid tooth skipping or jamming during operation.
Install the drive sprocket and the driven sprocket, ensuring that the clearance between them and the chain is ≤ 1.5mm, and apply special lubricating grease to reduce wear.
Connection between motor and reducer
The 4KW motor is directly connected to the reducer through a plum blossom coupling, and the coaxiality error is adjusted to ≤ 0.1mm. After wiring, the forward and reverse rotation functions are tested.
4、 Integration of functional components
Tooling tray positioning mechanism
Install the blocker and photoelectric sensor, adjust the triggering accuracy to ± 1mm, and achieve precise docking of the tray at the workstation.
Debugging of transfer device
Configure the lifting/translation mechanism, control the cylinder stroke through PLC (such as 300-600mm), and test the synchronization of the cross line transfer of the fixture board.
5、 System debugging and acceptance
No load trial operation
Start the motor to observe the running trajectory of the chain, detect abnormal vibration or noise, adjust the tension wheel to make the deflection of the chain ≤ 3%.
Load performance testing
Verify the load capacity according to the formula WA (kg/m)=(weight of material+pallet)/conveying distance, and verify the stability of full load operation at 15m/min.
Security protection inspection
Install an emergency stop button and protective cover to ensure that the emergency braking response time is ≤ 0.5 seconds, in compliance with mechanical safety standards.
6、 Additional explanation
Intelligent upgrade: Real time monitoring of operational data is achieved through MES system integration, optimizing production pace and fault warning.
Maintenance standard: It is recommended to replenish chain grease every 500 hours and regularly check the oil level of the motor carbon brush and reducer.
The above process, through modular assembly and precise debugging, can ensure that the conveyor line achieves a design speed of 30m/min and a bearing capacity of 2000kg/m ².